Overview                   
     Cedar                       
     Danka                       
     FSU                    
     Legrand                     
     Maritz TRBI                
     ProspectUs                
     SCA Hygiene             
     Solution 6                  
     STA Travel                
The Issues

Legrand UK began supplying electrical fittings in the UK in the 1970’s and today some 30 years later is one of the major players in the UK market producing solutions for domestic commercial and industrial applications.

Legrand employ over 25,000 staff in 51 countries and their operations in the UK were based around a diverse range of property in multiple locations. Unfortunately the use of property for the business was both ineffective and inefficient and in the face of tougher market conditions
there was an immediate need to gain competitive efficiencies and rationalise the UK distribution and manufacturing base.

Our Role

We were asked to act as Legrand’s corporate manager in the UK responsible for delivering their business plan. At its simplest we were presented with a short term challenge to identify a building to house and meet the business requirements of the UK operation whilst
maximising the use of infrastructure resources to ensure long term compatibility with a tough economic market.

Following extensive discussions with key decision makers to establish business goals and key performance indicators, a range of issues were identified as being key to meeting their needs:

• The required solution needed to meet the needs of the workforce in order to minimise work disruption and staff attrition.
• Operating limitations needed to be removed i.e. poor access and location
• The solution needed to be scalable in order to accommodate future scope and growth
• Costs needed to be minimised and the investment maximised in order to secure the best possible returns in a tough market.

Our Solution

• A demographic study of the workforce allowed a maximum radius to be defined. Using this and the building site requirements and we were able to locate four possible sites/properties which met objectives
• The developers of two of the four possible sites were approached at an early stage to examine a possible willingness to take the present properties as part of the overall deal.
• The sites were identified as allowing for certain regional assistant grants to be applied for.
• The plan had an occupancy date in terms of operational opening in September 1996 some two years after the initial study had been completed.
• Following a rigorous analysis of the local labour markets, cost, timing and flexibility the most appropriate location was deemed to be Central Gate, Newtown Road, Birmingham.
• We worked closely with Legrand to secure appropriate funding and in addition assembled a bespoke team to define requirement in terms of professional team, lawyers, designers, engineers, defining and briefing as appropriate.
• The team acted as development managers nurturing Legrand’s relationship with Birmingham City Council and the DTI promoting rapid definition of accommodation requirements and design and procurement programmes.

The Results

• Within 24 months the Project was completed. The ability to open a new building of approximately 120,000 sq ft to include 100,000 sq ft of production space and 20,000 sq ft of offices was considered a significant improvement to the business taking it into the new millennium.
• Our ability to identify imaginative solutions to cost and fund the project released significant benefits including:
a) Operational cost savings.
b) Reduced relocation costs.
c) Enhanced disposal receipts.
d) Synchronised acquisitions and disposals.
e) Additional tax and grant contributions
• The operational cost savings were shown to be £771,000
News and Publications
Property diligence
The hidden threats and opportunities
Is your building burning a hole in your bottom line?
Boardroom Briefings
Find out more...
About the Images
Click here to find out more